Progress billing cash calculator

What can you bill at this percent complete?

Your numbers

$
%
$

Explore the numbers

Examples, chart, and saved snapshots

Start with a realistic example, adjust the inputs, or save your numbers before experimenting.

Example 1

Forty percent of a 500,000 contract

The contract price is 500,000. Your estimate says the job is 40 percent complete. Previous bills total 150,000. Under the tax rule the percent is costs incurred divided by estimated total costs. A survey of work finished can go in the same box.

$50,000.00to bill now
Example 2

Contract price: 25% lower

Change contract price to 375,000 while keeping the other example values the same.

$0.00already matches this percent
Example 3

Contract price: 25% higher

Change contract price to 625,000 while keeping the other example values the same.

$100,000.00to bill now

Interactive chart

See what changes the result

Result—

The chart changes one input while holding all other current values steady. It is a sensitivity view, not a forecast.

Browser snapshots

Freeze these values

Save the current calculation, experiment freely, and restore it later.

No saved snapshots for this calculator yet.

Saved only in this browser. Nothing is uploaded, and clearing browser data removes the snapshots.

Quick answer

What does the Progress billing cash calculate?

What can you bill at this percent complete? This calculator uses contract price, percent complete, and previous bills to estimate work completed, minus bills already sent immediately in your browser.

With the values currently entered, the result is $50,000.00 — to bill now. It also shows earned to date, previous bills, and still unearned.

How to use the Progress billing cash

  1. Replace the example values with your own numbers.
  2. Review the result and supporting figures as they update automatically.
  3. Check the formula and assumptions before using the estimate for a decision.

Inputs used

  • Contract price
  • Percent complete — entered in %
  • Previous bills

Progress billing cash formula

Earned to date = contract price × percent complete. This bill = earned to date − previous bills.

Assumptions

  • 26 CFR 1.460-4 multiplies a completion factor by the total contract price, then subtracts the cumulative amount from the prior year. The regulation says that difference can be negative. This page uses the percent you type as the factor. Under the tax rule, the factor is costs incurred divided by estimated total contract costs.
  • FAR 52.232-5 pays progress payments on estimates of work accomplished that meet the contract’s quality standards. ASU 2014-09, paragraph 606-10-55-17, also measures progress with surveys of performance completed to date. This page does not hold retainage. A hold on the bill belongs on the retainage cash delay calculator.

Verify the inputs

Authoritative sources

These sources explain the definitions, factors, or rules behind this tool. Their geographic scope is shown because an official source for one country is not automatically valid somewhere else.

Sources do not endorse Calculum. Check the source date, scope, and your own documents before making a financial, tax, insurance, or reporting decision.

Practical guide

Progress billing cash example and edge cases

A progress bill prices the work finished so far, then subtracts the bills you already sent. 26 CFR 1.460-4 multiplies a completion factor by the contract price and subtracts the prior cumulative amount. FAR 52.232-5 pays on estimates of work accomplished.

Example: Forty percent of a 500,000 contract

The contract price is 500,000. Your estimate says the job is 40 percent complete. Previous bills total 150,000. Under the tax rule the percent is costs incurred divided by estimated total costs. A survey of work finished can go in the same box.

Contract price
500,000
Percent complete
40 %
Previous bills
150,000

Calculated result$50,000.00to bill now

Earned to date is 200,000. Previous bills are 150,000, so this bill is 50,000. The contract still has 300,000 unearned. Retainage, if the contract holds any, is a separate calculator.

Example results use the default display profile. The calculator above follows your selected country and units.

How to read the result

  • Read the 50,000 first. It is 200,000 earned minus 150,000 already billed. Forty percent of 500,000 is the 200,000. The regulation says the difference between this cumulative amount and the prior one can be negative.
  • FAR 52.232-5 wants an estimate of work accomplished that meets the contract quality standards. Paragraph 606-10-55-17 also allows a survey of performance completed to date. This page does not hold retainage on the 50,000.

Edge cases worth checking

Previous bills already pass the earned amount

If previous bills are 220,000 and the job is still 40 percent complete, earned to date stays 200,000. This bill is negative 20,000. You are overbilled against this percent. The regulation allows that difference to be negative when the estimate changes.

Stored material is outside the percent

FAR 52.232-5 lets the contracting officer count material delivered on site, and preparatory work, when building the estimate. Leave that material out of the percent and the earned amount misses it. Put it in the percent when the approved estimate includes it.

What changes the result most

Contract price

Use a current amount for contract price. Include fees or recurring costs that belong in the same figure.

Percent complete

Test a lower and higher percent complete. A small percentage change can move the final result more than expected.

Previous bills

Use a current amount for previous bills. Include fees or recurring costs that belong in the same figure.

Try a different scenario

Small changes show whether the answer is stable or sensitive.

Contract price: 25% lower

375,000

$0.00already matches this percent

Contract price: 25% higher

625,000

$100,000.00to bill now

Percent complete: 25% higher

50 %

$100,000.00to bill now

Common mistakes

Check contract price

26 CFR 1.460-4 multiplies a completion factor by the total contract price, then subtracts the cumulative amount from the prior year. The regulation says that difference can be negative. This page uses the percent you type as the factor. Under the tax rule, the factor is costs incurred divided by estimated total contract costs. Make sure this matches the number you enter.

Keep previous bills consistent

FAR 52.232-5 pays progress payments on estimates of work accomplished that meet the contract’s quality standards. ASU 2014-09, paragraph 606-10-55-17, also measures progress with surveys of performance completed to date. This page does not hold retainage. A hold on the bill belongs on the retainage cash delay calculator. Use the same units and time period throughout the calculation.

Do not rely on one progress billing cash scenario

Run a cautious case and an optimistic case. The range is often more useful than one exact-looking number.

Use this result well

Use it for

What can you bill at this percent complete?

Do not use it as

It does not replace a quote, contract, accountant, or local employment guidance.