Project internal rate of return calculator

What discount rate sets this project’s net present value to zero?

Your numbers

$
$
years
%

Explore the numbers

Examples, chart, and saved snapshots

Start with a realistic example, adjust the inputs, or save your numbers before experimenting.

Example 1

The same 50,000 project, solved for the rate

Spend 50,000. Collect 15,000 at the end of each year for five years. The rate that makes the present value of those inflows equal 50,000 is the IRR. The comparison hurdle stays at 8 percent so you can see NPV at a rate you already use.

15.2%internal rate of return
Example 2

Project outlay: 25% lower

Change project outlay to 37,500 while keeping the other example values the same.

28.6%internal rate of return
Example 3

Project outlay: 25% higher

Change project outlay to 62,500 while keeping the other example values the same.

6.4%internal rate of return

Interactive chart

See what changes the result

Result—

The chart changes one input while holding all other current values steady. It is a sensitivity view, not a forecast.

Browser snapshots

Freeze these values

Save the current calculation, experiment freely, and restore it later.

No saved snapshots for this calculator yet.

Saved only in this browser. Nothing is uploaded, and clearing browser data removes the snapshots.

Quick answer

What does the Project internal rate of return calculate?

What discount rate sets this project’s net present value to zero? This calculator uses project outlay, annual net cash inflow, years of inflows, and comparison hurdle rate to estimate discount rate that sets npv to zero immediately in your browser.

With the values currently entered, the result is 15.2% — internal rate of return. It also shows npv at the hurdle rate, undiscounted total inflows, project outlay, and comparison hurdle rate.

How to use the Project internal rate of return

  1. Replace the example values with your own numbers.
  2. Review the result and supporting figures as they update automatically.
  3. Check the formula and assumptions before using the estimate for a decision.

Inputs used

  • Project outlay
  • Annual net cash inflow
  • Years of inflows — entered in years
  • Comparison hurdle rate — entered in %

Project internal rate of return formula

IRR is the annual rate r that sets outlay = annual inflow × [1 − (1+r)^(−n)] ÷ r. NPV at the hurdle uses the same present-value sum.

Assumptions

  • DOE project-analysis methodology defines IRR as the discount rate at which net present value is zero.
  • Cash goes out once at the start. Equal inflows arrive at the end of each year. Extra outlays later can create more than one IRR and sit outside this solve.

Verify the inputs

Authoritative sources

These sources explain the definitions, factors, or rules behind this tool. Their geographic scope is shown because an official source for one country is not automatically valid somewhere else.

Sources do not endorse Calculum. Check the source date, scope, and your own documents before making a financial, tax, insurance, or reporting decision.

Practical guide

Project internal rate of return example and edge cases

Internal rate of return is the discount rate that sets NPV to zero. DOE project-analysis notes use that definition. On this page the cash shape is one outlay, then equal annual inflows.

Example: The same 50,000 project, solved for the rate

Spend 50,000. Collect 15,000 at the end of each year for five years. The rate that makes the present value of those inflows equal 50,000 is the IRR. The comparison hurdle stays at 8 percent so you can see NPV at a rate you already use.

Project outlay
50,000
Annual net cash inflow
15,000
Years of inflows
5 years
Comparison hurdle rate
8 %

Calculated result15.2%internal rate of return

IRR is 15.2 percent. NPV at the 8 percent hurdle is 9,890.65, the same leftover the NPV calculator prints. CAGR cannot replace this figure. CAGR only connects two balances, with no yearly inflow in between.

Example results use the default display profile. The calculator above follows your selected country and units.

How to read the result

  • Read IRR first. Then check NPV at the hurdle. If IRR sits above the hurdle, NPV at that hurdle is positive.
  • A negative IRR means even a 0 percent discount leaves a hole. Total inflows never cover the outlay.

Edge cases worth checking

You have a second cash outlay in year three

Two sign changes can create two IRRs. Stop and use NPV at a hurdle you trust. This solver assumes cash out once, then inflows.

You compared IRR with CAGR

CAGR turns a start value into an end value. IRR zeros a project NPV. They match only in special cases. Use each page for its own question.

What changes the result most

Project outlay

Use a current amount for project outlay. Include fees or recurring costs that belong in the same figure.

Annual net cash inflow

Use a current amount for annual net cash inflow. Include fees or recurring costs that belong in the same figure.

Years of inflows

Keep years of inflows on the same time basis as the other inputs. Monthly and annual values are easy to mix up.

Try a different scenario

Small changes show whether the answer is stable or sensitive.

Project outlay: 25% lower

37,500

28.6%internal rate of return

Project outlay: 25% higher

62,500

6.4%internal rate of return

Annual net cash inflow: 25% higher

18,750

25.4%internal rate of return

Common mistakes

Check project outlay

DOE project-analysis methodology defines IRR as the discount rate at which net present value is zero. Make sure this matches the number you enter.

Keep comparison hurdle rate consistent

Cash goes out once at the start. Equal inflows arrive at the end of each year. Extra outlays later can create more than one IRR and sit outside this solve. Use the same units and time period throughout the calculation.

Do not rely on one project internal rate of return scenario

Run a cautious case and an optimistic case. The range is often more useful than one exact-looking number.

Use this result well

Use it for

What discount rate sets this project’s net present value to zero?

Do not use it as

It does not replace a quote, contract, accountant, or local employment guidance.